Dec 8, 2008construction-lawciacarbitrationjurisdictione.o. 1008construction-disputes

CIAC Jurisdiction Prevails Over Arbitration Agreements in Construction Disputes

Learn how the Supreme Court affirmed CIAC's exclusive jurisdiction over construction disputes even when contracts name a different arbitration body.


The Supreme Court has long recognized the Construction Industry Arbitration Commission (CIAC) as the specialized forum for resolving construction disputes in the Philippines. In Heunghwa Industry Co., Ltd. v. DJ Builders Corporation (G.R. No. 169095, December 8, 2008), the Court clarified a crucial point: once parties agree to arbitration in a construction contract, the CIAC acquires jurisdiction over their disputes—even if the contract names a different arbitration institution. This ruling reinforces the primacy of CIAC jurisdiction and serves as a warning to parties who attempt to withdraw from arbitration after a dispute arises.

The Dispute: A Subcontractor Seeks Payment

Heunghwa Industry, a Korean corporation, secured a contract from the Department of Public Works and Highways to construct the Roxas-Langogan Road in Palawan. It then entered into a subcontract agreement with DJ Builders Corporation for earthwork, sub base course, and box culvert work worth over Php113 million. The subcontract contained an arbitration clause.

When Heunghwa failed to pay the full agreed price, DJ Builders filed a complaint before the Regional Trial Court (RTC) of Puerto Princesa for breach of contract and collection of sum of money. Both parties, through their counsels, later filed a Joint Motion to submit five specific issues to the CIAC for arbitration. The RTC granted this motion.

The Procedural Wrinkle: A Party Tries to Withdraw

After the CIAC began proceedings, Heunghwa moved to withdraw the referral, claiming its counsel had no authority to submit the case to arbitration. The RTC initially recalled its referral order, but the CIAC asserted jurisdiction, citing the arbitration clause in the subcontract agreement. The CIAC proceeded with the case and eventually awarded DJ Builders over Php31 million.

Heunghwa challenged the CIAC's jurisdiction before the Court of Appeals, which ruled against it. The Supreme Court affirmed.

The Ruling: Arbitration Clause Alone Vests CIAC with Jurisdiction

The Supreme Court held that the CIAC had original and exclusive jurisdiction over the dispute. Under Executive Order No. 1008 (1985), which created the CIAC, the Commission has jurisdiction over construction disputes provided the parties agreed to submit such disputes to arbitration.

The Court emphasized that the mere presence of an arbitration clause in a construction contract is sufficient to vest the CIAC with jurisdiction. This is true even if the contract names a different arbitration body, such as the International Chamber of Commerce. The Court cited the CIAC Rules of Procedure, which state that an arbitration clause in a construction contract "shall be deemed an agreement to submit an existing or future controversy to CIAC jurisdiction, notwithstanding the reference to a different arbitration institution or arbitral body."

Key Points from the Decision

No need for a separate submission agreement. Once parties agree to arbitration in their construction contract, a subsequent consent to submit a particular dispute to the CIAC is "superfluous and unnecessary."

Jurisdiction cannot be waived. Jurisdiction is conferred by law and cannot be defeated by a party's refusal to participate. The CIAC Rules allow arbitration to proceed even if a respondent refuses to appear.

A lawyer's alleged lack of authority is not a defense. Since the arbitration clause itself vested the CIAC with jurisdiction, the question of whether counsel was authorized to refer specific issues became immaterial.

Interlocutory orders generally cannot be challenged by certiorari. A denial of a motion to dismiss is an interlocutory order, not appealable through certiorari, unless there is a clear showing of grave abuse of discretion.

Practical Takeaways

  • For construction contractors and subcontractors: Including an arbitration clause in your contract effectively means you are agreeing to CIAC jurisdiction, regardless of what arbitration body the clause names.
  • For parties in a construction dispute: Attempting to withdraw from arbitration after proceedings begin will likely fail. The CIAC can proceed without your participation, and you risk losing your chance to present evidence.
  • For counsel: Be mindful that a client's attempt to disavow a counsel's referral to the CIAC will not defeat the Commission's jurisdiction if the contract contains an arbitration clause.
  • For parties considering a challenge: A denial of a motion to dismiss by the CIAC is generally not the proper subject of a petition for certiorari absent grave abuse of discretion.

This article is general information and not legal advice. For your specific situation, consult a lawyer or ask ASG Legal AI.

This article is general information and not legal advice. For your situation, ask ASG Legal AI or book a consultation.

CIAC Jurisdiction Prevails Over Arbitration Agreements in Construction Disputes · Ablola, Saribong & Gueco