Dec 4, 2023construction-lawarbitrationciacjurisdictionnon-signatoriesphilippine-supreme-court

Construction Arbitration: When Non-Signatories Are Bound by Arbitration Agreements

Philippine Supreme Court rules on when non-signatories to a construction contract can be bound by its arbitration clause, clarifying CIAC jurisdiction.


The Supreme Court recently clarified a critical question in Philippine construction law: when can a party who did not sign a construction contract still be bound by its arbitration clause? In The Consortium of Hyundai Engineering Co., Ltd. and Hyundai Corporation v. National Grid Corporation of the Philippines (G.R. Nos. 214743 and 248753, December 4, 2023), the Court ruled that a non-signatory may be compelled to arbitrate if it has a "significant and substantial connection" to the construction contract. This decision is essential reading for project owners, contractors, and concessionaires navigating construction disputes.

The Dispute

Hyundai entered into a construction contract with the National Transmission Corporation (TransCo) for a transmission backbone project. The contract contained an arbitration clause requiring disputes to be submitted to arbitration. Later, TransCo entered into a Concession Agreement with the National Grid Corporation of the Philippines (NGCP) and a separate Construction Management Agreement, under which NGCP took over TransCo's transmission business and managed its ongoing projects.

When a dispute arose over liquidated damages for delay, Hyundai filed a request for arbitration before the Construction Industry Arbitration Commission (CIAC), impleading both TransCo and NGCP. NGCP moved to dismiss, arguing that it was not a party to the construction contract and therefore not bound by its arbitration clause.

The Issue

The central question was whether the CIAC had jurisdiction over NGCP, a non-signatory to the construction contract containing the arbitration agreement.

The Ruling

The Supreme Court ruled in favor of Hyundai, holding that the CIAC had jurisdiction over NGCP. The Court explained that while arbitration agreements generally bind only the parties who signed them, Philippine law and jurisprudence recognize exceptions. Under Section 35 of Republic Act No. 9285 (the Alternative Dispute Resolution Act of 2004), CIAC jurisdiction extends to disputes "between or among parties to, or who are otherwise bound by, an arbitration agreement, directly or by reference."

The Court applied the "significant and substantial connection" test. In earlier cases, this test bound sureties under performance bonds to arbitration clauses in construction contracts because their obligations were inseparable from the contractor's obligations. Here, the Court found that the Concession Agreement and Construction Management Agreement were "significantly and substantially linked" to the construction contract because they defined NGCP's role in the project and the extent to which it assumed TransCo's duties. NGCP had actively dealt with Hyundai in implementing the contract, and the dispute over liquidated damages arose directly from the construction contract's provisions.

The Court also rejected the Court of Appeals' ruling that arbitration would be ineffectual without NGCP. The CIAC could fully resolve the dispute between the parties bound by the arbitration agreement.

Practical Takeaways

  • Non-signatories can be bound by arbitration clauses. A party with a "significant and substantial connection" to a construction contract may be compelled to arbitrate even without signing it. This includes entities that assume rights and obligations under the contract through related agreements.
  • Review related contracts carefully. Concession agreements, management agreements, and assignment documents can bind parties to arbitration clauses in underlying contracts. Parties should assess their exposure before assuming roles in construction projects.
  • CIAC jurisdiction is broad. The CIAC has original and exclusive jurisdiction over disputes arising from or connected with construction contracts in the Philippines, provided the parties agreed to arbitration. This jurisdiction can extend to non-signatories with sufficient ties to the contract.
  • Actively participating in contract implementation matters. Dealing with the contractor, managing the project, and exercising rights under the contract can strengthen the case for binding a non-signatory to arbitration.
  • Seek early legal advice. Before moving to dismiss arbitration proceedings on jurisdictional grounds, parties should consider whether their connection to the construction contract might subject them to CIAC jurisdiction.

This article is general information and not legal advice. For your specific situation, consult a lawyer or ask ASG Legal AI.

This article is general information and not legal advice. For your situation, ask ASG Legal AI or book a consultation.