Perfected Construction Contract Award Trumps Suspension
A bidder's acceptance of a notice to proceed perfects a construction contract; a later suspension does not undo it. The Supreme Court explains.
The Supreme Court has ruled that a construction contract is perfected the moment a bidder accepts the owner's notice of award, and a subsequent suspension of work does not negate that perfected contract. In Metro Rail Transit Development Corporation v. Gammon Philippines, Inc. (G.R. No. 200401, January 17, 2018), the Court also affirmed that factual findings of the Construction Industry Arbitration Commission (CIAC) are final and binding, except in narrow circumstances.
The case arose from the MRT-3 North Triangle Project, a 54-hectare development that included a commercial center with a podium structure. Gammon Philippines, Inc. won the bid for the podium's concrete works and received a Letter of Award and Notice to Proceed on August 27, 1997. Gammon signed and returned the notice on September 2, 1997, and transmitted the formal contract documents on September 9, 1997.
Days later, MRT suspended the project to study the effects of foreign exchange fluctuations and rising interest rates. MRT later downscaled the project, issued several amended notices to proceed, and eventually awarded the construction contract to another company. Gammon filed claims before CIAC for lost profits and reimbursement of expenses incurred for engineering services, design work, and site de-watering.
The Issues
The case presented four main questions: whether a perfected contract existed between MRT and Gammon; whether the doctrine of law of the case applied; whether MRT was bound by its admission in its Answer that it was willing to pay a specific amount; and whether Gammon's claims for damages were sufficiently proven.
Perfection of the Contract
The Court ruled that a perfected contract existed. Under Article 1315 of the Civil Code, contracts are perfected by mere consent. Article 1318 requires consent, object, and cause. The Court explained that in bidding contracts, the award of the contract to the bidder is an acceptance of the bidder's offer, which perfects the contract upon notice of the award to the bidder.
MRT argued that it withdrew its offer before Gammon returned the contract documents. The Court disagreed. The September 8, 1997 letter from MRT merely stated that it needed time to study the effects of foreign exchange rates before issuing a formal notice to proceed. This was a suspension of work, not a withdrawal of the offer. The Court noted that MRT found it necessary to expressly cancel the First Notice to Proceed in its Fourth Notice to Proceed, which implied that a contract had indeed been perfected.
The Limits of Appeal from CIAC Awards
The Court emphasized that CIAC is a quasi-judicial agency created under Executive Order No. 1008 to settle construction disputes expeditiously. Under Section 19 of the Construction Industry Arbitration Law, arbitral awards are final and unappealable except on questions of law.
The Court reiterated that CIAC's factual findings are conclusive and not reviewable on appeal, except when the award was procured by fraud, corruption, or undue means; when there was evident partiality of the arbitrators; or when the arbitrators exceeded their powers. MRT failed to prove any of these exceptions.
The Award for Damages
The Court upheld CIAC's award of P58,642,969.62, which included P5,493,639.27 for engineering services, design work, and site de-watering, plus P53,149,330.35 for lost profits. The Court noted that MRT's Answer with Compulsory Counterclaim contained an admission that it was willing to pay the amount for reimbursements. While MRT argued this was merely an offer to settle, the Court found it binding.
The Court also rejected MRT's argument that the lost profits claim was unsubstantiated. CIAC's factual findings on the amount of damages were entitled to respect and finality.
Practical Takeaways
-
A notice of award and notice to proceed, once accepted by the bidder, perfects a construction contract. A subsequent suspension of work does not undo that perfection.
-
Owners who suspend projects after awarding a contract may still be liable for breach of contract, including lost profits and reimbursement of expenses incurred by the contractor.
-
CIAC arbitral awards are final and binding on questions of fact. Appeals are limited to pure questions of law.
-
A party's admission in its pleadings, such as an Answer stating a willingness to pay a specific amount, can be binding and treated as a judicial admission.
-
Contractors should document all expenses incurred during mobilization and suspension, as these may be recoverable even if the contract is later awarded to another party.
This article is general information and not legal advice. For your specific situation, consult a lawyer or ask ASG Legal AI.
This article is general information and not legal advice. For your situation, ask ASG Legal AI or book a consultation.