Premature Demolition and Due Process: When Property Rights Clash with Fair Play
A Supreme Court ruling on how premature demolition violates due process and the abuse of rights principle under Article 19 of the Civil Code.
The right to own property is a cornerstone of Philippine law, but it is not absolute. A 2001 Supreme Court decision reminds property owners that exercising their rights must always be tempered by justice, honesty, and good faith. In Rellosa v. Pellosis (G.R. No. 138964), the Court held that demolishing a structure before the owner's appeal period lapses is a violation of due process—even if the demolition order is later affirmed on appeal.
The Facts of the Case
Respondents were long-time lessees of a parcel of land in Malate, Manila, owned by Marta Reyes. They had built houses on the property and made continuous improvements over the years. When Marta died, her son Victor inherited the land. In 1986, Victor informed the lessees that, having occupied the land for over twenty years, they had a right of first refusal to buy it.
In early 1989, without the lessees' knowledge, the land was sold to petitioner Cynthia Ortega, who eventually secured title in her name. On 25 May 1989, Ortega filed a petition for condemnation of the structures with the Office of the Building Official of Manila. The lessees, in turn, filed a civil suit questioning the sale based on their right of first refusal.
After hearings, the Building Official issued a resolution on 27 November 1989 ordering the demolition of the lessees' houses. Copies were served on 7 December 1989. The very next day, Ortega and her father hired workers to start demolition. Only the timely intervention of police prevented the destruction. On 11 December 1989, the lessees filed their administrative appeal. The following day, petitioners again hired workers and demolished the houses.
The Issue
Was the petitioners' act of demolishing the houses before the appeal period expired a legal wrong that entitles the lessees to damages, even though the demolition order was later affirmed on appeal?
The Ruling
The Supreme Court ruled in favor of the lessees. The Court emphasized that under the Implementing Rules and Regulations of Presidential Decree No. 1096 (the National Building Code), parties adversely affected by a Building Official's resolution have fifteen days from receipt to perfect an administrative appeal. Until that period lapses, the resolution is not yet final and executory.
The petitioners implemented the demolition barely five days after the lessees received the resolution—well within the appeal period. This precipitate action effectively deprived the lessees of their right to contest the ruling. The Court noted that the fact the demolition order was later affirmed by the Department of Public Works and Highways was "of no moment." What mattered was that petitioners acted in disregard of the lessees' procedural rights.
The Abuse of Rights Principle
The Court anchored its decision on Article 19 of the Civil Code, which provides that "every person must, in the exercise of his rights and in the performance of his duties, act with justice, give everyone his due, and observe honesty and good faith." This provision is not merely a declaration of principle; it can itself be a valid source of a cause of action when ignored.
While the petitioners were the owners of the land with the right to enjoy and dispose of it, the exercise of these rights has limitations. When a right is exercised in a manner that discards the norms of justice and good faith, resulting in damage to another, a legal wrong is committed for which the actor can be held accountable. The Court clarified that the issue was not the existence of the demolition order but whether petitioners acted in conformity with the standards set by law.
The Court reduced the damages awarded by the Court of Appeals, however, finding the original amounts excessive. Each respondent was awarded P20,000.00 in moral damages and P20,000.00 in exemplary damages, instead of P75,000.00 each.
Practical Takeaways
- Respect appeal periods. A demolition order is not final and executory until the appeal period lapses. Acting before then violates due process.
- Article 19 is a potent legal tool. Even when exercising a valid right, acting in bad faith or with disregard for others' rights can create liability for damages.
- Later affirmation does not cure premature action. The fact that an order is eventually upheld on appeal does not excuse implementing it too early.
- Property rights are not absolute. Ownership carries the duty to act with justice, honesty, and good faith toward others.
- Damages may be reduced on appeal. While wrongful demolition warrants compensation, courts will calibrate awards to what is reasonable under the circumstances.
This article is general information and not legal advice. For your specific situation, consult a lawyer or ask ASG Legal AI.