Dec 4, 2018quantum meruitgovernment contractscommission on auditmoney claimspublic works

Quantum Meruit Claims Against the Government: Payment for Services Without a Written Contract

The Supreme Court clarifies when contractors can recover payment from the government on quantum meruit even without a written contract.


The Supreme Court has long recognized that the government must pay for services it actually benefits from, even when no formal written contract exists. In Geronimo v. Commission on Audit (G.R. No. 224163, December 4, 2018), the Court ruled that a contractor who completed landscaping projects for the Department of Public Works and Highways (DPWH) without a written agreement was entitled to compensation on the basis of quantum meruit—a Latin phrase meaning "as much as he deserves."

The case clarifies an important principle for anyone who has rendered services to a government agency under informal arrangements: the absence of a written contract does not automatically bar recovery, provided the government acknowledged the services and benefited from them.

The Facts of the Case

In February 2005, DPWH officials invited Mario Geronimo, doing business as Kabukiran Garden, to a meeting. The agency needed landscaping and beautification work done along major thoroughfares in Metro Manila—including Ayala Boulevard, Roxas Boulevard, and Osmeña Highway—in time for the 112th Inter-Parliamentary Union (IPU) Summit.

Because time was short, DPWH verbally commissioned Geronimo to implement the projects without executing any written contract. Officials assured him he would be paid in full upon completion. Geronimo finished the projects in July 2005, incurring costs totaling P14,245,994.20.

Despite several demands, the DPWH failed to pay. Geronimo filed a money claim with the Commission on Audit (COA).

The COA's Contradictory Ruling

The COA made a significant finding: based on the memoranda and endorsement letters from DPWH officials, the agency had acknowledged its obligation to Geronimo. The COA even concluded that quantum meruit applied.

However, the COA still denied the claim, citing Section 4(6) of Presidential Decree No. 1445 (the Government Auditing Code), which requires that claims against government funds be supported by complete documentation. The COA said Geronimo lacked documents to substantiate the projects' completion and the reasonableness of the costs.

The Supreme Court's Ruling

The Supreme Court sided with Geronimo, reversing the COA's decision. The Court emphasized two key points.

First, the principle of quantum meruit applies to government contracts. The Court cited Dr. Eslao v. Commission on Audit (273 Phil. 97 [1991]), which held that a contractor should be compensated despite the failure to conduct public bidding, because denying the claim would result in the government unjustly enriching itself. The Court also referenced Royal Trust Construction v. Commission on Audit, a case involving the widening and deepening of the Betis River in Pampanga, where recovery was allowed even without a written contract and covering appropriation, because the work was impliedly authorized and expressly acknowledged by the government agency.

Second, the DPWH's liability was sufficiently established. The Court noted that the COA itself found that DPWH acknowledged its obligation. Internal memoranda from DPWH officials—including one from then-Undersecretary Florante Soriquez referring to "claims for payment of completed beautification projects"—confirmed the agency's recognition of liability. Another memorandum suggested charging the payment against the DPWH's Engineering and Administrative Overhead or available funds.

The Court found that the COA gravely abused its discretion when it denied the claim despite recognizing Geronimo's entitlement. While the documents may have been insufficient to determine the exact amount due, the proper remedy was to require additional evidence or employ auditing techniques to ascertain a reasonable value—not to deny the claim outright.

Practical Takeaways

  • A written contract is not always required for government payment. Courts will apply quantum meruit when the government agency impliedly authorized the work and later acknowledged its obligation.
  • Documentation matters. Keep photographs, correspondence, memoranda, and any written acknowledgment from government officials. These can establish that the agency recognized the services and their benefit to the public.
  • The government cannot unjustly enrich itself. Where services clearly redounded to public benefit, equity demands compensation even if formal requirements were not followed.
  • COA findings are not absolute. While generally given great respect, COA decisions may be reversed if they are arbitrary or constitute grave abuse of discretion.
  • Expect the COA to determine the amount. When a claim is recognized, the COA should compute the reasonable value of services on a quantum meruit basis rather than deny payment entirely.

This article is general information and not legal advice. For your specific situation, consult a lawyer or ask ASG Legal AI.

This article is general information and not legal advice. For your situation, ask ASG Legal AI or book a consultation.

Quantum Meruit Claims Against the Government: Payment for Services Without a Written Contract · Ablola, Saribong & Gueco