Right of Way vs Contractual Obligations: Enforcing Compromise Agreements in Property Development

Philippine Supreme Court clarifies when courts may review factual findings and how contractual penalties are reduced in breach cases.


The Supreme Court recently clarified important principles on contractual obligations and penalties in construction agreements. The case of Swire Realty Development Corporation v. Specialty Contracts General and Construction Services, Inc. (G.R. No. 188027, August 9, 2017) addressed when appellate courts may review factual findings and how courts should treat penalty clauses in breached contracts. This ruling provides valuable guidance for property developers, contractors, and parties entering into construction or service agreements.

The Dispute

Swire Realty engaged Specialty Contracts to perform waterproofing works on the Garden View Tower condominium project for PHP 2 million. The agreement required completion within 100 calendar days. Specialty Contracts accomplished only 90% of the work and failed to complete the remaining portion despite demands. Swire then hired another contractor, Esicor, to finish the unfinished work.

The trial court ruled in favor of Swire, awarding actual damages and attorney's fees. The Court of Appeals reversed, finding that additional works were performed and ordering Swire to pay Specialty Contracts. The Supreme Court reviewed the case.

The Issue

Two main questions were raised: First, whether the Supreme Court could review the factual findings of the Court of Appeals in a petition for review on certiorari. Second, whether the waterproofing of the swimming pool constituted additional work requiring separate compensation.

The Court's Ruling

The Supreme Court ruled in favor of Swire Realty, reversing the Court of Appeals' decision. The Court found that the waterproofing of the swimming pool was already included in the original scope of works under the agreement. The swimming pool was expressly listed as a covered area in the contract, and the contractor should have raised any claim for additional compensation before performing the work.

The Court emphasized that under the agreement's change order provisions, any additional work should have been subject to prior agreement between the parties. A mere instruction to redo waterproofing did not automatically constitute additional work when the area was already within the contract's scope.

Key Principles Established

The ruling clarified several important legal principles:

Review of factual findings. While petitions for review on certiorari generally raise only questions of law, the Court may review factual findings when the Court of Appeals' conclusions are based on misapprehension of facts or contradict the trial court's findings.

Contractual penalties. The Court applied Articles 1229 and 2227 of the Civil Code, which allow courts to equitably reduce penalties when the principal obligation has been partly complied with or when the penalty is iniquitous or unconscionable. The contractor's delay of 365 days would have resulted in a penalty of PHP 3.65 million, but the Court reduced this to PHP 200,000 considering that 90% of the work was completed and there was no bad faith.

Attorney's fees. The Court deleted the award of attorney's fees, citing Philippine National Construction Corporation v. APAC Marketing Corporation, which requires factual and legal justification for such awards. A mere statement that a party was constrained to litigate is insufficient.

Practical Takeaways

  • Scope of work should be explicit. Contractors should carefully review the scope of work and raise concerns before performing any work that may fall outside the agreement. Performing work without prior agreement on additional compensation may result in non-payment.

  • Follow change order procedures. Construction contracts typically require written notice and agreement for changes. Contractors who perform work without following these procedures risk being unable to claim additional compensation.

  • Penalty clauses are not absolute. Courts may reduce contractual penalties that are iniquitous or unconscionable, especially when the obligor has substantially complied with the obligation.

  • Document everything. Courts rely on evidence to determine the extent of work accomplished. Proper documentation of instructions, site forms, and progress billings is crucial.

  • Attorney's fees require justification. Parties seeking attorney's fees must present specific factual and legal bases, not merely claim that they were forced to litigate.