Mar 26, 2003arbitrationconstruction lawalternative dispute resolutioncontract lawciacsupreme court

Upholding Arbitration Agreements in Construction Disputes: The LM Power Case

Philippine Supreme Court affirms that courts should liberally construe arbitration clauses, requiring parties to honor their agreement to arbitrate construction disputes.


The Supreme Court has long encouraged alternative dispute resolution (ADR) methods like arbitration, mediation, and conciliation to help parties settle their conflicts more quickly and amicably. In LM Power Engineering Corporation v. Capitol Industrial Construction Groups, Inc. (G.R. No. 141833, March 26, 2003), the Court reaffirmed a key principle: when parties agree to arbitrate, courts should respect that agreement and liberally construe arbitration clauses in favor of arbitration. This ruling provides important guidance for businesses and individuals involved in construction contracts and other commercial agreements.

The Facts of the Case

In 1983, LM Power Engineering Corporation entered into a Subcontract Agreement with Capitol Industrial Construction Groups, Inc. for electrical work at the Third Port of Zamboanga. When a dispute arose over payments, LM Power filed a collection case in court instead of going to arbitration. Capitol moved to dismiss the case, arguing that the contract required the parties to submit their dispute to arbitration first.

The trial court denied the motion to dismiss and eventually ruled in favor of LM Power. On appeal, however, the Court of Appeals reversed the decision and ordered the parties to present their dispute to arbitration. The case reached the Supreme Court, which had to determine whether the dispute was covered by the arbitration clause in the parties' agreement.

The Arbitration Clause

The Subcontract Agreement contained a clause stating that "any dispute or conflict as regards to interpretation and implementation of this Agreement which cannot be settled amicably shall be settled by means of arbitration." LM Power argued that its claim was simply a collection case and did not involve interpretation or implementation of the contract.

The Supreme Court disagreed. The Court found that the parties differed on several key questions: whether a take-over of work constituted termination, whether expenses could be set off against amounts owed, and how much was actually due under the contract. Resolving these issues required interpreting the contract's provisions on time schedules, termination, and payment terms. The Court held that these were exactly the kinds of disputes the parties had agreed to arbitrate.

Courts Should Liberally Construe Arbitration Clauses

The Court emphasized an important policy: consistent with encouraging ADR, courts should liberally construe arbitration clauses. If a clause can reasonably be interpreted to cover the dispute at issue, an order to arbitrate should be granted. Any doubt should be resolved in favor of arbitration.

The Court also noted that arbitration is an inexpensive, speedy, and amicable method of settling disputes. It helps unclog judicial dockets and hastens the resolution of commercial disputes. "Brushing aside a contractual agreement calling for arbitration between the parties would be a step backward," the Court stated.

No Need for Prior Request to CIAC

LM Power also argued that the Construction Industry Arbitration Commission (CIAC) could not acquire jurisdiction because no formal request for arbitration had been filed. The Court rejected this argument, explaining that under the old CIAC rules, a party needed to submit a request for arbitration. However, the new rules dispensed with this requirement.

Under the current rules, an arbitration clause in a construction contract is deemed an agreement to submit disputes to CIAC jurisdiction. It is no longer necessary for parties to enter into a separate submission agreement before a claimant may invoke CIAC's jurisdiction. As long as the parties agreed to submit to voluntary arbitration, their dispute may fall within CIAC's jurisdiction, even if they named a different arbitration body in their contract.

What This Means for Contracting Parties

The ruling underscores several important points. First, arbitration clauses are binding commitments that parties must honor in good faith. Second, courts will not allow a party to avoid arbitration by characterizing a dispute as something outside the contract's scope when the dispute genuinely requires interpreting the agreement. Third, a party who files a court case despite an arbitration clause may have that case stayed or suspended so that arbitration can proceed.

The proper procedure for a party who wants to compel arbitration is to ask the court to stay the civil action under Section 7 of Republic Act No. 876, the Arbitration Law. This provision allows a court to suspend proceedings when it is satisfied that the issue involved is referable to arbitration.

Practical Takeaways

  • If a contract contains an arbitration clause, courts will generally require the parties to arbitrate disputes that fall within its scope, even if one party prefers to litigate.
  • Arbitration clauses should be drafted broadly to cover disputes over interpretation, implementation, and performance of the contract.
  • Courts liberally construe arbitration clauses and resolve any doubt in favor of arbitration.
  • Under current CIAC rules, a construction contract with an arbitration clause is sufficient to invoke CIAC jurisdiction without a separate submission agreement.
  • A party seeking to compel arbitration should file a motion to stay the court action under RA 876 rather than simply refusing to participate in the litigation.

This article is general information and not legal advice. For your specific situation, consult a lawyer or ask ASG Legal AI.

This article is general information and not legal advice. For your situation, ask ASG Legal AI or book a consultation.