Mar 25, 2015civil procedurefailure to prosecuteres judicataconstruction contractdamagessupreme court

Upholding Court Authority Disregarding Orders Constitutes Contempt

The Supreme Court affirms that a party disregarding court orders and delaying proceedings may face dismissal of its case and liability for damages.


The Supreme Court recently reaffirmed a fundamental principle of Philippine litigation: courts have the authority to dismiss cases when parties repeatedly disregard orders and delay proceedings. In FAJ Construction & Development Corporation v. Saulog (G.R. No. 200759, March 25, 2015), the Court also clarified important rules on construction contracts, damages, and the binding effect of counsel's mistakes on clients.

The Case Background

FAJ Construction entered into an agreement with Susan Saulog to build a residential building in Makati City for P12,500,000.00. Saulog paid over P10.5 million, but refused to pay the remaining balance of P851,601.58, claiming the work was defective. FAJ terminated the contract and sued for collection.

The case took a critical turn when FAJ repeatedly failed to appear for trial. Despite several postponements and a warning from the trial court, FAJ and its counsel missed hearings on April 29, 2003 and September 4, 2003. The trial court dismissed the complaint for failure to prosecute.

The Issue

The central question was whether the dismissal of FAJ's complaint was proper, and whether FAJ could still challenge that dismissal after the Supreme Court had already denied its earlier petition questioning the same dismissal.

The Ruling

The Supreme Court denied FAJ's petition and affirmed the Court of Appeals' decision. The Court held that FAJ's attempt to relitigate the dismissal of its complaint was barred by res judicata — the principle that a matter already finally decided cannot be raised again.

The Court explained that when it denies a petition through a minute resolution, that denial constitutes an actual adjudication on the merits. Once final and executory, the parties cannot revisit the issue.

Key Principles Established

Mistakes of counsel bind the client. The Court rejected FAJ's argument that it should not suffer for its lawyer's negligence. The general rule is that counsel's mistakes bind the client. Notably, FAJ continued retaining its counsel even after witnessing the lawyer's performance during trial, only changing lawyers after the adverse decision on the counterclaim.

The Supreme Court is not a trier of facts. Petitions for review on certiorari under Rule 45 may only raise questions of law. The Court refused to re-examine the evidence on defective workmanship and damages, especially since the trial court and Court of Appeals had identical factual findings.

Defective work and abandonment. Under Article 1715 of the Civil Code, a contractor must execute work with the qualities agreed upon and without defects. When the contractor fails to comply, the employer may have defects removed or work redone at the contractor's cost. The Court found FAJ liable for defective and incomplete work, delay, and unjustified abandonment.

Damages must be proven. The Court of Appeals deleted awards for lost rentals, moral damages, exemplary damages, and attorney's fees because these were not adequately proven. Actual damages must be proved with reasonable certainty — courts cannot rely on speculation or self-serving allegations.

Penalty for delay. The construction agreement provided for P12,500.00 per day of delay. FAJ was delayed by approximately 270 days, which would have meant P3,375,000.00 in liquidated damages. The courts awarded only P1,387,500.00, which the Supreme Court found liberal and not excessive.

Interest on damages. When an obligation not constituting a loan is breached, courts may impose interest at 6% per annum on the damages awarded, from the filing of the complaint until full satisfaction.

Practical Takeaways

  • Respect court orders and deadlines. Repeated failure to appear or comply with court directives can result in dismissal of a case for failure to prosecute, which may be final and binding.
  • Clients are bound by their lawyers' actions. While courts may grant relief for gross negligence of counsel, this is the exception, not the rule. Clients should monitor their cases actively.
  • Final judgments are truly final. Once a dismissal is affirmed and becomes final, it cannot be relitigated through a different procedural vehicle.
  • Damages require proof. Claims for actual damages, lost profits, and moral damages must be supported by competent evidence, not mere allegations.
  • Contractual penalties are enforceable. Agreed penalty clauses for delay are binding, and courts will generally uphold them unless they are clearly excessive.

This article is general information and not legal advice. For your specific situation, consult a lawyer or ask ASG Legal AI.

This article is general information and not legal advice. For your situation, ask ASG Legal AI or book a consultation.